Embodied carbon in structures is the greenhouse gas released by making, transporting, building, maintaining and eventually demolishing the structural frame of a building, everything except the energy used to run it. In the UAE the largest share usually sits in concrete and reinforcement, which means the structural engineer’s early decisions on grade, member sizing and material specification do more to lower it than any later fix. This guide explains what the figure includes, how it is measured, how steel and concrete compare, and which choices reduce it on Dubai and wider UAE projects.
TL;DR
- Embodied carbon covers material extraction, manufacturing, transport, construction, maintenance, replacement and end-of-life, but not operational energy.
- It is calculated by multiplying each material quantity by its carbon factor, and a credible report states its factors, quantities and assumptions.
- Neither steel nor concrete wins in every case: the result depends on the mix, the recycled content, the member design and the quantities.
- In the UAE, cement replacement with fly ash and slag, recycled steel and leaner structural design are the proven levers, and they work best when set at concept stage.
Table of Contents
- What embodied carbon includes
- Embodied versus operational carbon
- How embodied carbon is measured and reported
- Steel versus concrete: what the comparison depends on
- Embodied carbon in UAE concrete
- Design choices that reduce embodied carbon
- Regulation, ratings and what clients are asking for
- Our perspective
- Working with Integra on a lower-carbon structure
- FAQ
- Sources
What embodied carbon includes
The US Department of Energy describes embodied carbon as the emissions tied to the extraction, manufacturing, transportation, installation, maintenance, replacement and end-of-life disposal of building materials. In life-cycle terms it is the total over a building’s life excluding operational energy, which sits in modules B6 and B7.
For a structural engineer this translates into a simple picture. Every cubic meter of concrete, every tonne of reinforcement and every steel section carries an emissions footprint before it reaches site. Cement production is the heaviest contributor in concrete, and primary steelmaking is the heaviest in steel. Transport to site, crane and pumping energy, formwork, and waste add smaller layers on top.
The life-cycle modules matter because they decide what a number means. Cradle-to-gate (A1 to A3) covers raw materials, transport to the factory and manufacturing. Later modules cover construction, use, end of life (C1 to C4) and the benefits beyond the system boundary (D). When two figures are compared, they have to share the same boundary, otherwise the comparison says nothing.
Embodied versus operational carbon
Operational emissions come from a building’s function: cooling, lighting, appliances and maintenance, while embodied emissions come from construction and deconstruction. In a hot climate like the UAE, cooling has long dominated the operational side, which is why efficiency measures have attracted most of the attention.
That balance is shifting. Academic work published in Buildings and Cities finds that as operational efficiency improves, embodied carbon’s relative and absolute share of life-cycle emissions grows and can become dominant in energy-efficient buildings. The practical consequence is that a highly efficient tower still carries a large carbon debt from its frame on the day it opens. Operational savings arrive slowly over decades; embodied emissions are spent immediately, during construction.
This is also why the structure deserves attention. The frame, foundations and slabs are typically the heaviest material systems in a building, and their quantities are fixed by design decisions made in the first months of a project.
How embodied carbon is measured and reported
The method is straightforward in principle. According to the Engineers and Geoscientists BC guide, you multiply the quantity of each material in kilograms by its carbon factor in kgCO2e per kilogram, across the life-cycle modules you have chosen to cover. The work lies in getting trustworthy quantities and factors.
Quantities
Quantities come from the structural model and the bill of quantities: concrete volume by grade, reinforcement tonnage, structural steel tonnage, post-tensioning, formwork and any façade or fixings you include in scope. Rebar density (kg per cubic meter of concrete) is a useful sanity check, because an unusually high figure often points to an inefficient design or an unresolved detailing issue.
Carbon factors
The best factor is a product-specific Environmental Product Declaration from the actual supplier. Where none exists, generic database values are used and flagged as such. For concrete, factors vary strongly with the cement content and the proportion of supplementary cementitious materials, so a single generic value for “C40 concrete” can hide a wide spread.
Reporting
The UK Green Building Council advises that reports state project information, emission factors and their sources, material quantities and key assumptions, and that a quality-assurance process is in place. In practice, that means a client or authority reading the report should be able to reproduce the result from the inputs.
A workable sequence for a design team looks like this:
- Fix the scope and life-cycle modules at briefing stage, so every option is judged on the same basis.
- Run a quick quantity-based estimate on the concept structural scheme.
- Compare two or three structural options, such as flat slab versus post-tensioned slab, or a composite versus concrete frame.
- Replace generic factors with supplier declarations as procurement firms up.
- Update the figure at detailed design and again against as-built quantities.
For Dubai projects, the same exercise feeds sustainability submissions, a subject we cover in our guide to calculating embodied carbon in Dubai developments.
Steel versus concrete: what the comparison depends on
Designers often ask which material is greener. A 2023 academic study from the UAE, Assessment of building materials in the construction sector, found that concrete typically contributes a higher percentage of a structure’s embodied carbon than steel in many cases, but that comparisons vary. Its conclusion points to the strategies that matter: optimized concrete mixes using supplementary cementitious materials, and steel with a high recycled content.
The honest answer is that the comparison turns on a handful of variables:
| Factor | Concrete structure | Steel structure |
|---|---|---|
| Main source of emissions | Cement content in the mix | Primary versus recycled steelmaking route |
| Biggest lever | Replacing clinker with fly ash, slag or blended cement | Specifying high recycled content steel with a supplier declaration |
| Design lever | Slab depth, grid, grade by element, rebar efficiency | Member optimization, connection simplicity, composite action |
| Often overlooked | Lightweight mixes can carry higher emissions than normal-weight mixes | Fire protection, coatings and fabrication waste |
| Durability factor | Cover and exposure class in coastal conditions | Corrosion protection and maintenance cycle |
The lightweight concrete point comes from the structural engineers’ SE2050 design guidance, which notes that lightweight mixes can have significantly higher embodied carbon than normal-weight mixes because of the emissions linked to the lightweight aggregate. It is a good reminder that a lighter structure is not automatically a lower-carbon one.
Durability belongs in the comparison too. A structure that needs early repair carries replacement and maintenance emissions in modules B2 to B5. Coastal Dubai’s chloride and carbonation exposure is a real design driver, which we discuss in our note on concrete carbonation and chloride attack in coastal Dubai.
The fairest method is to design both options properly, quantify them on the same boundary, and then decide on carbon, cost, programme, fire strategy and constructability together. Steel buildings often win on speed and weight, concrete on thermal mass, robustness and local supply. Carbon is one input to the decision, not the whole decision.
Embodied carbon in UAE concrete
Concrete is the dominant structural material in the Emirates, so its mix design is where most reductions are found. The EmiratesGBC document Low Carbon Materials in the UAE explains that emissions can be cut by reducing clinker through supplementary cementitious materials and blended cements, and it notes that Dubai Municipality Circular 225 mandates their use across multiple grades in line with BS 8500-1.
The circular itself dates from July 2018 and sets out the Dubai Sustainable Concrete Baseline, with baseline mixes using GGBS, fly ash and silica fume alongside OPC. It also directs that design engineers are consulted on the durability specification for each project, based on service life, exposure and cover. That reminder matters: a low-carbon mix is only acceptable when it meets the durability requirement of the site.
There is also useful local data on cement. The same EmiratesGBC document reports that, as of 2026, low-carbon cement produced for the UAE market by Holcim has a cradle-to-gate global warming potential of approximately 727 kg CO2e per tonne, which it describes as a 10% reduction against pure OPC and up to 25% against broader market averages. The document’s wider message is that low-carbon solutions are commercially mature and available in the UAE, and that locally manufactured blended cements can lower carbon intensity while meeting performance standards.
What the Dubai case study showed
The 2023 study cited above analyzed a G+2 building in Dubai. Careful material selection and life-cycle assessment in the early stages produced a 26% reduction in embodied carbon. At material level, industry-average ready-mix C60 concrete at 442.96 kgCO2e per cubic meter fell to 344.7 kgCO2e per cubic meter, a 22% reduction, while reinforcement steel dropped from 0.62 to 0.50 kgCO2e per kilogram, a 19% reduction, in the study’s actual scenario. These are results for one building and one set of assumptions, so treat them as an illustration of the scale of what is possible, not a promise for every project.
For teams that want the durability and Eurocode side of the same decision, our overview of reinforced concrete design in the UAE covers the design basis, and our piece on recycled aggregates in concrete looks at another material route.
Design choices that reduce embodied carbon
The most reliable way to cut emissions is to use less material. Structural engineers can do that without compromising safety, and the order of the levers below reflects how much each one usually delivers.
Optimize the structure first
Regular grids, efficient spans, sensible slab systems and element-by-element concrete grades reduce volume before any low-carbon product is specified. A column designed for C60 on the lower floors does not need that grade at the top. Value engineering, done properly, is a carbon tool as much as a cost tool, because cutting unneeded material cuts both.
Change the mix, not the performance
Specify cement replacement with fly ash or ground granulated blast-furnace slag where the programme and durability allow it. Early-age strength gain is slower with high replacement levels, so formwork striking times and post-tensioning stressing dates must be planned with the contractor from the start.
Choose steel by its route
Recycled steel lowers the footprint of reinforcement and sections, as the EmiratesGBC document confirms. Ask suppliers for declarations that state the recycled content and the production route, and compare them on the same life-cycle boundary.
Consider alternative construction methods
A full-scale UAE case study of 3D printing with a self-reinforced printable mortar found significantly lower global warming potential than conventional concrete construction, reported in the Sustainability journal. It is still a niche method, but it shows where material efficiency can lead.
Keep what already stands
Retaining and strengthening an existing structure avoids the carbon of demolition and a new frame. A strength evaluation followed by targeted strengthening is often the lowest-carbon option for ageing assets, as in our work on structural integrity assessments for ageing buildings in Deira and Bur Dubai and in retrofitting and strengthening projects.
Do not forget foundations
Piles and rafts can account for a large share of a low-rise or mid-rise building’s structural carbon. Pile length optimization, load testing to justify design capacities and low-carbon mixes all help, and we set these out in our guide to sustainable foundation engineering with carbon-reduced piling.
Regulation, ratings and what clients are asking for
The regulatory picture in the UAE is moving from guidance to practice. Dubai’s concrete baseline is a clear example of an authority shaping material choices, and the EmiratesGBC document describes cement decarbonization as standard industry practice, supported by Dubai Municipality circulars and the adoption of blended cements.
For structural teams, the practical route to demonstrating performance is through the green building framework that applies to the project. We have written about Dubai’s Al Sa’fat 2.0 requirements for new permits, the structural compliance side of Al Sa’fat, and the choice between Estidama Pearl and LEED. For the wider policy context, see our article on sustainable structural engineering and the UAE Net Zero 2050 goal.
We advise owners to confirm the current applicable requirements with the authority at the start of design, because rating criteria and circulars are updated over time.
Our perspective
We see embodied carbon as a design-stage question that is answered by engineering judgment, not by a label added at handover. The most effective reductions we have seen come from three habits: questioning every quantity in the structural scheme, specifying materials by performance rather than by habit, and agreeing the durability and approval strategy with the authority before drawings are issued.
Our practice is built on designing in ACI, Eurocode and British Standards for the UAE, Dubai, Saudi Arabia and other Gulf countries, and that dual fluency is what lets us integrate international codes with local requirements. It means a lower-carbon mix or a leaner frame can be justified clearly to Dubai Municipality and DDA, which keeps approvals efficient.
We therefore treat value engineering and design optimization as one discipline. A frame that uses less concrete and steel is cheaper to build, quicker to erect and lighter on the planet, and it does not need to compromise architectural quality.
Aman
Working with Integra on a lower-carbon structure
If you are a developer, contractor or asset owner planning a project in the UAE, we can help you bring embodied carbon into the structural design from the outset: concrete and steel design, value engineering and design optimization, and authority submissions to Dubai Municipality and DDA. Explore our structural design services or talk to us about authority approvals and structural analysis.
For projects where programme risk is high, our guide to managing structural design risk in fast-track Dubai projects explains how early carbon decisions fit into a compressed schedule.
FAQ
What is the difference between embodied and operational carbon?
Operational carbon comes from running a building: cooling, lighting and appliances. Embodied carbon comes from making, transporting, constructing, maintaining and demolishing the materials, excluding operational energy. As buildings become more efficient, embodied carbon makes up a growing share of the life-cycle total.
Is steel or concrete better for embodied carbon?
Neither wins in every case. Concrete often contributes a larger share in many structures, but the result depends on cement content, recycled steel content, member design and quantities. Compare both options on the same life-cycle boundary using supplier declarations, then weigh carbon alongside cost, programme and durability.
Can low-carbon concrete be used in Dubai?
Yes. Dubai Municipality Circular 225 sets baseline mixes that use GGBS, fly ash and silica fume, and locally produced blended cements are available. The mix must still meet the durability specification the design engineer sets for the site’s exposure, cover and service life.
When should embodied carbon be assessed on a project?
At concept stage, when the structural system, grid and material strategy are still open. The Dubai case study above credits early-stage material selection and life-cycle assessment for its 26% reduction. Update the figure at detailed design and again against as-built quantities.
Sources
- Embodied Carbon Reduction in New Construction, US Department of Energy
- Embodied versus operational carbon emissions in buildings, Global ABC
- Embodied carbon emissions in buildings, Buildings and Cities
- How to calculate embodied carbon, Engineers and Geoscientists BC
- Embodied carbon: improving your modelling and reporting, UKGBC
- Assessment of building materials in the construction sector, PMC
- Low Carbon Materials in the UAE, EmiratesGBC
- Circular 225 Attachment 2, Dubai Municipality
- Environmental footprint and economics of a full-scale 3D-printed house, Sustainability
- SE2050 design guidance