RFI management in construction is the discipline of raising, routing, answering and recording formal requests for information so that every clarification on drawings, specifications or site conditions is resolved quickly and leaves a written trail. In the UAE, where design teams, contractors and authorities such as Dubai Municipality, DDA and DEWA all touch the same project, a clear RFI process protects both the programme and the contractual record. This guide sets out the workflow, the content of a complete RFI, the difference between an RFI and a submittal, realistic response times and the points that are specific to Dubai.
TL;DR
- An RFI is a formal written question about drawings, specifications, contract documents or site conditions. Raise one only when the answer is not already in the approved documents.
- A good RFI carries one question, exact references, a marked-up sketch or photo, a proposed solution and a response date tied to the work sequence.
- An RFI asks for clarification. A submittal asks for approval of something the contractor proposes to supply or build.
- Log every RFI in a register with submission, due and actual response dates, and escalate overdue items at progress meetings with the affected activity named.
- In Dubai, RFIs on authority-controlled work sit alongside DDA drawing standards and DEWA NOCs, so the design consultant should manage them together.
Table of Contents
- What an RFI is and when to raise one
- The RFI process from first question to closeout
- What a complete RFI contains
- RFI vs submittal
- RFI response time: what to allow and how to chase
- RFI management best practices
- Managing RFIs on UAE and Dubai projects
- Our perspective
- How Integra supports your RFI and approval workflow
- FAQ
- Sources
What an RFI is and when to raise one
An RFI is a formal written request for clarification about drawings, specifications, contract documents or project conditions, used to close information gaps and to document a decision. Procore describes typical subjects as design clarifications, requested design changes, permitted substitutions, constructability issues and differing site conditions. PlanRadar adds that a team should raise one when a detail is unclear, two documents conflict, a site condition differs from the design, or a material or installation requirement needs confirmation before work can proceed correctly.
The opposite rule matters as much. Before issuing an RFI, the contractor should check the approved drawings, specifications, contract documents, meeting minutes and earlier instructions. If the answer is already recorded in one of them, the RFI is inappropriate, and it costs the designer time that the project could have spent on genuine queries. Procore also notes that an RFI is not a routine communication, a safety plan, a schedule, a transmittal or a substitute for issuing required design documents.
In practice, the best RFIs on a Dubai project come from a site engineer who has read the structural drawings, the architectural set and the specification together, and has found a point where they disagree. A slab thickness that differs between a structural section and an architectural detail, a sleeve that clashes with a beam, or a rebar congestion point at a column-beam joint are all good examples. A request such as “please confirm the paint colour already shown in the schedule” is not.
The RFI process from first question to closeout
The sequence is similar on almost every project, whether it runs on a spreadsheet or on a platform. The GSA’s published workflow is a clear public example: the originator enters a subject and question, attaches documents or photos, names the primary responder and a due date, and submits for review by the coordinator or owner’s representative. The request is then routed to the primary or secondary responders, the response is recorded and distributed, and the RFI is marked complete or returned for clarification.
Software vendors describe the same logic. Autodesk’s default workflow covers creation and submission, manager review, reviewer assignment, tracked responses, selection or composition of the official response, and distribution to the project team. Its enhanced workflow adds a coordination layer for complex projects, with coordinator review, expert review, response coordination and closure. The tool is secondary. What matters is that the stages are visible and each has an owner.
For a typical contractor-led project in the UAE, we find it useful to think in seven steps.
1. Check and frame the question
The originator confirms that the approved documents do not already answer it, and reduces the issue to a single question. Combining three queries in one RFI delays all three, because the answer cannot be issued until the slowest part is resolved.
2. Draft with evidence
The RFI is given a unique number and a subject that names the element and location. Sheet, detail and specification references are added, together with a marked-up drawing or photograph and a proposed solution.
3. Route to the right person
The request goes to the person able to answer it, usually the design consultant’s discipline engineer, with affected parties copied. Where the main contractor sits between a subcontractor and the design team, Linarc describes the subcontractor RFI passing through the general contractor before it reaches the architect or engineer, and the answer returning along the same path.
4. Respond in writing
The designer answers on the RFI itself, referencing revised drawings where the answer changes the design. A verbal answer on site is only useful if it is written back into the register the same day.
5. Distribute
The official response goes to everyone who relies on it: the contractor, subcontractors, the supervision team and, where relevant, the cost consultant.
6. Assess impact
If the answer changes cost, time or sequence, the contractor opens the appropriate variation or change notice under the contract. An RFI response is not automatically an instruction to vary the works, and the contract should be read before assuming either way.
7. Close and record
The RFI is closed with the date of the final response, linked to the revised drawing, and left reopenable in case the answer proves incomplete.
What a complete RFI contains
Incomplete RFIs are the commonest reason for slow answers. Published checklists agree closely. OS Construction’s checklist recommends a unique subject identifying the element and location, one clear question, sheet, detail or specification references, the conflict or gap, a proposed solution, cost and schedule impact, a required response date and a marked-up sheet or photo.
PlanRadar’s list for a complete RFI is wider: reference number, submitter and assigned reviewer, discipline or work package, exact location or zone, drawing and specification references, a description of the issue, the question itself, supporting photographs, sketches or markups, the required response date, and potential time, cost, quality or sequence impact. Procore stresses stating the precise misunderstanding, the affected parties, the impacted process and the date a response is needed.
A short example shows the difference. A weak RFI reads: “Column clash on level 3, please advise.” A strong one reads: “RFI 042, Level 3, grid C/4. Structural drawing S-203 detail 5 shows a 300 mm deep transfer beam; the architectural ceiling section A-410 shows a 2.75 m clear height requiring a maximum 250 mm beam. Please confirm which governs. We propose to keep the 300 mm beam and lower the ceiling locally. Concrete pour is scheduled in ten working days, and the answer is needed before formwork fixing.” The second version can be answered in one pass, because the designer has the references, the proposal and the deadline in front of them.
The proposed solution deserves emphasis. It shows the contractor has considered buildability, and it often shortens the designer’s work to a yes, a no or a small adjustment. It also keeps the design responsibility where the contract places it, with the designer.
RFI vs submittal
The two are often confused because both travel through the same register and both involve the design team. The difference is the purpose. An RFI asks a question: what does this detail mean, which document governs, is this condition acceptable. A submittal presents something for approval: shop drawings, material samples, product data, method statements or mock-ups, which the contractor proposes to build or supply and the designer reviews against the design intent.
Procore’s guidance is explicit that an RFI is not a submittal, and mixing them causes real problems. A submittal has its own review period and its own approval status codes, while an RFI ends with an answer. If a contractor uses an RFI to seek approval of a substituted material, the response may not carry the formal approval the contract requires. If a submittal is used to ask an open design question, it can bounce back marked “revise and resubmit” without ever answering it.
A useful rule: if you are asking the designer to tell you something, raise an RFI. If you are asking the designer to accept something you have prepared, raise a submittal. Shop drawings are the clearest case. Our own guide on shop drawings versus design drawings explains how clean shop drawings save a review cycle on Dubai projects, and many RFIs on steel and precast work disappear once the detailing intent is agreed before fabrication drawings are issued.
There is also a contractual angle. Under FIDIC-based contracts, the handling of delayed drawings and instructions is tied to notice requirements, and the Institute of Construction Claims Practitioners warns that approval-dependent submittals may also fall within that framework, so notice compliance should be checked against the contract itself. Where a clause, a notice period or an entitlement is in question, the contract and a qualified claims adviser decide, not a general guide.
RFI response time: what to allow and how to chase
There is no universal figure, because the contract sets the period. The sensible approach, in line with the OS Construction checklist, is to set the due date from the field need while staying within the contractual response period. A reinforcement query for a slab to be poured in three days cannot be treated like a finishes clarification for next quarter.
One industry report, from Construction AI, puts the average RFI response at about 10 working days against contract requirements that typically sit between 5 and 7. It is a single vendor’s figure rather than a regional benchmark, but the gap is familiar to anyone who has chased an answer. It also recommends keeping every RFI in a register, reviewing outstanding items weekly and escalating overdue ones at progress meetings.
The escalation message matters. State the activity that is blocked and the consequence of a missed answer, for example that formwork on level 3 cannot proceed and the pour will slip by a stated number of days. A request that reads as a programme risk gets attention that a polite reminder does not.
Escalation meetings also expose the human side of RFIs. Contractor, designer and client each carry different pressures, and a meeting that treats an overdue RFI as blame rarely resolves it. Facilitation practice on competing needs and unspoken tension in groups is a useful reminder that naming the shared deadline first tends to move people faster than naming the delay.
A short list of habits keeps response times honest. Assign each RFI to a named person rather than a department. Keep a weekly review of all open items. Agree at kick-off which RFIs the designer will answer within two or three days, such as those that block concrete pours, and which can follow the standard period.
RFI management best practices
The checklists from OS Construction and others converge on a short set of habits that we recognize from live projects:
- One question per RFI, assigned to someone able to answer it, with affected parties on distribution.
- A number for every RFI, logged immediately, with the ball-in-court party visible. OS Construction’s documentation records the RFI number, responsible party, responses, attachments, official response, notifications and closed date, and lets closed RFIs be reopened.
- Marked-up evidence rather than prose alone.
- The RFI number written on the revised drawing, so site teams can trace why a detail changed.
- A change event opened if the answer alters cost or time.
- A closed date recorded for every item.
Procore’s perspective is that RFIs protect the project by turning information gaps and decisions into a shared written record, which reduces corrective work and ambiguity. That record also supports good document control. Our document control plan for practitioners shows how RFIs, drawing revisions and transmittals can be tied into one controlled register, and our guide to construction project management places the RFI log within the wider reporting cycle.
The register has a second life as evidence. If a delay claim arises, a register showing each request, its submission date, the date a response was required and the date it actually arrived demonstrates both the contractor’s diligence and the response performance of the design team. Entitlement to more time still depends on the contract, notice and critical-path impact, so the register supports a claim rather than guaranteeing one.
Managing RFIs on UAE and Dubai projects
The mechanics are the same as anywhere, but three local factors change how teams should run them.
Authority-controlled drawings
On projects in DDA-regulated zones, drawings issued in response to an RFI may need to follow the authority’s presentation rules. DDA’s Circular 400 on drawing submission standards requires drawings to be monochrome apart from specified presentation materials, arranged sequentially and submitted under the appropriate discipline tab such as architecture, structural, mechanical or fit-out. A revised detail that arrives as a coloured markup is perfect for the site but cannot be forwarded to the authority as it stands. Plan for a clean revised sheet whenever an RFI response changes a permitted drawing. DDA also states in its general FAQ that planning and building applications go through Zoning eServices, where applicants can follow the request status online.
Utility approvals
When an RFI concerns services or infrastructure, the answer may depend on an approval outside the design team. DEWA requires infrastructure NOCs before work starts for relevant road, network, general, house-connection and building-permit work, and lists Design, Construction, Trial Trench, Service Information, Shop Drawing and Design & Build NOC types. Its published service times are 3 working days for information, trial-pit, house-connection and DBPS NOCs, 5 for general projects and 7 for network and road projects, with longer periods possible in special cases. A designer cannot answer an RFI faster than the approval it depends on, so the register should show which RFIs wait on an authority and what the published time is. Check DEWA’s page for the current figures before relying on them.
Contract form and notice
Many UAE projects use FIDIC-based forms, where the engineer’s duty to issue drawings and instructions and the contractor’s duty to give timely notice interact. Written RFIs are the practical way to request a missing drawing or instruction. The notice periods and the effect of silence are matters for the particular contract, and a contracts specialist should review them before a dispute rather than after. Our overview of building contracting covers how contract structure shapes project delivery.
Our perspective
We approach RFIs as a design-quality signal as much as a project-control tool. When a contractor raises the same type of question repeatedly, such as conflicts between structural and architectural levels or unclear connection details, the cause usually sits upstream in the design package, and the most efficient answer is to fix the package rather than answer each query.
That is why we align structural design with the requirements of Dubai Municipality and DDA from the outset, using ACI, Eurocode and British Standards as the project requires, and why we coordinate drawings with the other disciplines before issue. Fewer ambiguities at submission means fewer RFIs on site, and fewer rounds with the authority.
When RFIs do arise, we answer them with the programme in mind. A response that names the revised detail, the affected drawings and the consequence for the sequence allows the contractor to proceed with confidence. We also support clients with construction supervision so that site work follows the stamped drawings, and with construction risk management so that information gaps are identified as risks before they become delays.
Aman
How Integra supports your RFI and approval workflow
Integra Consulting Services is a civil, structural and architectural engineering consultancy in Dubai. We design concrete, steel, timber, pre-engineered, tensile fabric, curtain wall and temporary works structures, and we manage Dubai Municipality and DDA submissions, authority approvals and construction supervision, so that design intent, authority requirements and site questions are handled by one team.
If you are planning a project and want a design package that generates fewer RFIs, or you need a consultant to answer site queries within your programme, discuss your project with us through our Dubai Municipality and DDA submission and approvals services or review the full range on our services page. For the wider picture on design risk, our article on how civil engineering consultants in Dubai mitigate project risks is a good next read.
FAQ
What is the difference between an RFI and an RFP?
An RFI during construction is a question about the project documents or site conditions, answered by the designer or owner’s representative. An RFP, a request for proposal, is a procurement document in which a client invites providers to bid for work. They belong to different stages and have different outcomes: one clarifies the design, the other selects a provider.
Who answers an RFI on a UAE project?
The person or party able to resolve the question, usually the design consultant’s discipline engineer, or the owner’s representative when the issue is about scope or conditions. Contractors and site teams normally submit to the consultant, designer, engineer or project owner, and the routing is set in the project procedures and contract.
How long should an RFI response take?
The contract sets the period, and a reported industry figure puts typical contract requirements at 5 to 7 working days, while actual averages run longer. Set the due date from the work sequence within the contractual period, review open items weekly and escalate overdue ones at progress meetings.
Do I need software to manage RFIs?
No. A numbered register with the submission date, due date, actual response date, responsible party and closed date is enough for a small project. Platforms add automatic routing and notifications, which helps on larger projects with many parties.
Can an RFI support a delay claim?
A well-kept register can evidence the information gap, the contractor’s diligence and the response performance of the design team. Entitlement to extra time still depends on the contract, notice and critical-path impact, so take advice from a contracts specialist before relying on it.
Sources
- RFIs: A Contractor’s Guide to Requests for Information, Procore
- RFI in Construction: How to Manage Site Clarifications Faster, PlanRadar
- Request for information, GSA
- Getting Started with RFIs in Forma Build, Autodesk
- RFI Workflow, Linarc
- RFI checklist, OS Construction
- RFIs in the OS Construction app
- RFIs in Construction: How to Get Answers Without Losing Time, Construction AI
- FIDIC Red Book: Delayed Drawings and Instructions, Institute of Construction Claims Practitioners
- Circular 400: Drawings Submission Standards, DDA
- FAQs General, DDA Zoning eServices
- Infrastructure Projects No Objection Certificate, DEWA
- Group facilitation, competing needs and unspoken tension, ELIS Advantage