The Trakhees approval process is a sequence of linked submissions, not a single permit. Trakhees is the regulatory arm of the Ports, Customs & Free Zone Corporation (PCFC). It reviews design, construction and environment, health and safety (EHS) matters for projects within its jurisdiction. A project moves from accreditation and design review, through the building permit and EHS documentation, to inspections and a completion certificate. Most delays come from a missing accreditation, an incomplete risk assessment or a safety plan that was never tied to the design. This guide sets out the sequence, the documents each stage requires and the points where applications stall.

Integradxb
Coordinate Engineering for Trakhees Submissions
Integra provides civil and structural engineering consultancy for UAE projects, with design informed by relevant standards and value engineering.

Explore engineering services

TL;DR

Table of Contents

Who Trakhees is and when its approval applies

Trakhees administers health, safety, environmental and planning regulations in specialized zones. According to SmartQHSE’s overview of Trakhees HSE, these include JAFZA, Port Jebel Ali, Port Rashid, Dubai Maritime City and Dubai Industrial City. Dubai Municipality governs the rest of the mainland plots, and the Dubai Development Authority governs its own free zones. The first question for any owner or developer is therefore which authority holds the plot, because every later step depends on the answer.

Owners who are unsure how the three authorities divide responsibility will find the comparison useful in our guide to Trakhees versus Dubai Municipality approvals. A wider view across all three is in our comparative approval guide for Dubai zones. Confirm the plot authority before any drawings are issued, since a design prepared to the wrong authority’s code has to be reworked.

The same system also applies to smaller works. A modification to an existing unit has its own application form for a modification permit or NOC, which distinguishes between retail and office, landlord, unit and industrial submissions. New construction goes through the building permit route. Both routes share the same logic: an accredited party submits, Trakhees reviews, and the works are checked on site.

Step 1: Accreditation comes before design

Trakhees runs an Accreditation Program intended to secure quality and performance in design, construction and HSE across all projects in its jurisdiction. Consultants and contractors working on these projects need valid accreditation, and the staff who prepare and supervise the work are covered by the same requirement.

In practice, this is the step that catches applicants unprepared. A technically sound design submitted through a consultant or contractor without a valid Trakhees accreditation ID card is likely to be rejected before anyone reviews the engineering. Before appointing any party, verify that the card is current and covers the discipline concerned.

The accreditation site also lists training programs. As of 2026, the Building Regulations and Design Guidelines courses for architecture, structural and MEP are listed at AED 3,750 each, and the Safety Advisor Registration Scheme (new) at AED 2,100, according to the Trakhees accreditation portal. Most owners will never take these courses themselves. The figures are a reminder that accreditation represents real investment by the firms that hold it, and that it is worth asking a prospective consultant to show it.

Step 2: Concept design and the regulations that govern it

Trakhees publishes design guidelines, known as the Building Regulations and Design Guidelines books, with separate volumes by discipline. The architecture book, often called the Blue Code, sets out what each submission stage must contain. These documents are the reference your design team works to, and a reviewer will check against them.

The concept stage is where later problems are cheapest to prevent. Decide the structural system, the intended use of the building and the likely safety hazards together. Industry practice, as described in the research behind this guide, is that safety planning added late tends to force redesign during construction. A fuller treatment of the structural side is in our guide to Trakhees authority regulations for structural submissions.

For projects in specific districts, the rules differ in detail. Owners building on the island, for instance, can read our explanation of Trakhees approvals on Palm Jumeirah. Industrial owners in free zones will find the structural focus in our note on Trakhees structural approval in JAFZA.

Step 3: The building permit submission

The building permit stage is the core design review. Trakhees uses a standard Building Permit Application form, which records the client details, the Trakhees ID, the trade license number for companies or the passport number for individuals, and the type of submission.

According to the Blue Code architecture book, the building permit stage requires architectural and structural drawings along with calculations. A typical package therefore contains the following.

Element What the reviewer checks
Application form and client identity Correct Trakhees ID, trade license or passport, and submission type
Architectural drawings Layout, boundary, utilities and refuse arrangements, conformity with the design guidelines
Structural drawings and calculations Code basis, loads, member design, foundation design, consistency with the architecture
Accreditation details Valid ID cards for the consultant and contractor
Safety documents Risk assessment and EHS plans linked to the physical scope

The structural calculations deserve special care. The Gulf practice of combining ACI, Eurocode and British Standards means the design basis must be stated clearly, so that the reviewer can follow which code governs which element. Mixed or unstated bases are a common source of technical comments. Our engineers prepare structural packages with the basis declared on the first page for this reason.

Step 4: EHS documents, risk assessment and method statements

The EHS side runs next to the design side. Trakhees expects risk assessment (RA) studies and project-specific EHS plans to accompany the engineering drawings. Even small works such as racking installations or minor fit-outs need an RA and method statements. The common failure is to treat these as paperwork added at the end, so that the document describes a site that does not match the drawings.

A reviewer or inspector will compare the safety plan with what is built. An RA that names hazards generic to any site, rather than the actual structure, lifting arrangements and access routes, is likely to attract comments. Write the RA from the drawings, and revise it whenever the design changes.

The discipline of identifying risk before approval is not unique to Dubai. For a general explanation of the idea in a permitting context, see what approval risk assessment means for land-use projects. In Trakhees terms, the principle is the same: identify the hazards early, record how each is controlled, and let that record shape the design. Our own construction risk management and Design for Safety service is built around this approach.

Occupational safety obligations continue after approval. Trakhees Regulation IO-4.0 on Occupational Health & Safety addresses the occupational health and safety aspects of industrial operations that clients, contractors and third-party companies must follow in the jurisdiction. Operators in industrial zones should read it when planning the operational phase, not only the build.

Step 4: EHS documents, risk assessment and method statements — overview diagram

Step 5: Construction, inspections and the Certificate of Conformity

Approval does not end with the permit. Inspections are scheduled at defined points. One example is the request for structural inspection prior to concreting, which is listed as a Trakhees service for building regulations and permits. Contractors should plan their pour schedule around inspection lead time, since a pour made without the required inspection can create costly consequences.

The Certificate of Conformity (COC) and other verified documents should be kept available on site. Trakhees can inspect without warning, and missing paperwork is an avoidable finding. Keep a controlled folder with the stamped drawings, the approved EHS plan, accreditation cards, inspection records and the latest method statements.

Site supervision is the practical safeguard here. Checking that what is built matches the stamped drawings is the purpose of construction supervision quality assurance against stamped structural drawings. It also produces the inspection records that the completion stage depends on.

Step 6: Completion certificates

The lifecycle ends with a Building Completion Certificate (BCC) for new buildings or a Modification Completion Certificate (MCC) for modifications. The research behind this article is clear that a completion certificate cannot be issued while the separate EHS requirements remain open. That is why the two workflows must run in parallel. A structural sign-off held up by an outstanding safety check is among the most frustrating delays, and the most preventable.

A sensible closing checklist has five items: all inspections recorded as passed, the COC on file, the EHS documents closed out, the as-built information consistent with the approved drawings, and the accreditation cards still valid on the date of application.

Why applications are rejected or delayed

The pattern is consistent across the sources we reviewed. The causes below account for most of the lost time.

Cause How to prevent it
Consultant or contractor not accredited Check each accreditation ID card before appointing, and again before submitting
Generic or missing risk assessment Prepare a site-specific RA from the drawings at concept stage
Safety plan not linked to physical scope Review the EHS plan whenever the design changes
Design basis unclear State the governing codes and loads on the first page of the calculations
Wrong authority Confirm whether the plot falls under Trakhees, Dubai Municipality or the DDA
EHS and design run in sequence Run both workflows in parallel from the start

None of these is a technical failure of engineering. They are failures of coordination, and coordination is the thing an experienced consultant adds.

How long does it take?

We do not quote a fixed duration. Review time depends on the completeness of the first submission, the number of technical comments and how quickly the design team answers them. Each round of comments adds time, so the most effective way to shorten the process is to submit a complete, accredited and internally consistent package the first time. Ask your consultant for a realistic timeline for your specific plot and scope, and ask what assumptions sit behind it.

Our perspective: approvals are an engineering coordination task

We see the Trakhees process as a coordination problem more than a paperwork problem. The engineering is usually sound by the time a package is ready. What delays projects is the gap between disciplines: a structural design that assumes one safety arrangement, a risk assessment that describes another, and a contractor whose accreditation lapsed in between.

Our approach is to build the submission as a single set from the start. We work in ACI, Eurocode and British Standards for projects in the UAE, Saudi Arabia and elsewhere in the Gulf, and we state the design basis plainly so the reviewer does not have to infer it. We keep the structural drawings, the calculations and the safety documentation consistent as the design develops, because a late change in one is the usual cause of a comment in another.

We also encourage owners to involve the engineer before the architecture is fixed. Value engineering at concept stage, for example, can reduce structural cost and simplify the review, whereas the same exercise after approval means resubmission. The earlier the conversation, the fewer the surprises.

— Aman

Support with Trakhees and other authority submissions

If your plot sits within a Trakhees zone, or you are weighing which authority applies, our team prepares structural analysis and design, manages authority approvals and supervises construction. Details are on our Dubai Municipality, DDA and authority approvals page, and the full range of design disciplines, from concrete and steel to temporary works, is listed on our services page.

Frequently asked questions

Who is Trakhees in Dubai?

Trakhees is the regulatory arm of the Ports, Customs & Free Zone Corporation. It administers health, safety, environmental and planning regulations in zones such as JAFZA, Port Jebel Ali, Port Rashid, Dubai Maritime City and Dubai Industrial City. Projects there need Trakhees approval rather than Dubai Municipality approval.

How do I get Trakhees approval?

Appoint an accredited consultant and contractor, then submit the building permit application with architectural and structural drawings and calculations. Prepare the risk assessment and EHS plans alongside them. Approval then continues through inspections to the completion certificate.

Is Trakhees approval the same as an EHS approval?

No. They are related but separate workflows. The building permit covers design and construction review, while EHS covers environment, health and safety requirements. A completion certificate depends on both being satisfied, so they should be run in parallel.

Why was my Trakhees submission rejected?

The most frequent cause is a submission from a consultant or contractor without valid Trakhees accreditation. Other common causes are a missing or generic risk assessment, safety documents not matched to the design, and an unclear design basis. Check each before resubmitting.